The forest department has told the company to stop, saying work began without the National Board for Wildlife’s approval. The notice came hours after the revised project cost became public.
Mumbai: Work on Adani Green Energy’s 1,500 MW Tarali pumped storage project in Maharashtra’s Satara district has been stopped, with the state forest department saying the project went ahead without the clearance of the National Board for Wildlife. The notice came within hours of the project’s revised cost figure becoming public, a figure that would cut the company’s wildlife conservation payment from Rs 227 crore to about Rs 2.27 crore. [Add the issuing authority, date and the exact work covered by the notice.]
The two numbers at the centre
The dispute turns on a simple piece of arithmetic. On February 23, 2026, the State Board for Wildlife imposed 15 conditions on the project, one of which required the company to deposit 4% of the project cost into the Sahyadri Tiger Reserve’s bank account. On the original estimate of Rs 5,675 crore, that came to Rs 227 crore. Maharashtra’s Principal Chief Conservator of Forests (Wildlife), M. Srinivas Reddy, wrote to the company in March asking it to pay that amount and to give an undertaking on the other 14 conditions.
Later, a revised affidavit put the project’s cost at Rs 56.75 crore, a cut of 99%. At 4%, that works out at about Rs 2.27 crore. The company deposited Rs 56.75 lakh, which is 1% of the revised figure, with the balance to be paid after National Board for Wildlife approval.
Conflicting accounts inside the department
The state’s own officials appear to have given different accounts of what happened next. According to reports, the forest department accepted the revised figure in October, but the chief wildlife official denied this in November. That inconsistency is one of the questions the state inquiry is expected to examine.
How the complaint began
The issue was raised by Rohan Bhate, the Honorary Wildlife Warden of Satara district, who filed a complaint on October 30 through the Prime Minister’s grievance portal and with the Maharashtra Chief Minister. On November 6, the Union Environment Ministry directed the Maharashtra Forest Department to investigate the matter on priority, and the state department has also begun an inquiry. Bhate questioned how a project estimated at Rs 5,675 crore could be assigned a cost of Rs 56.75 crore.
Adani Green’s response
The company has rejected the allegations. In a statement on Friday, a spokesperson called the claims “completely misleading.” The company said the figure on the online forest and wildlife portal was solely for site investigation and survey work, while the State Board for Wildlife considered the total project cost of Rs 5,675 crore. It also said the allegation that the revision was intended to lower conservation costs is false.
Adani Green added that the project is on private, non-forest land, about 3.2 km from the Koyna Wildlife Sanctuary and outside the notified buffer zone of the Sahyadri Tiger Reserve, and that it does not affect any tiger corridor or notified eco-sensitive zone. The Union Environment Ministry’s own clearance papers list Sahyadri Tiger Reserve and Koyna as the nearest protected areas, at about 1.5 km and 3.2 km, and require the company to obtain National Board for Wildlife clearance if applicable.
The political reaction
The Congress has demanded a Joint Parliamentary Committee investigation into the Adani Group. General Secretary Jairam Ramesh described the matter as a scandal of gigantic proportions, saying a project approved at Rs 5,675 crore was shown to cost only Rs 56.75 crore in a revised affidavit. These are the party’s allegations, and no finding has been made.
What is still unresolved
The key question is whether the lower figure was a genuine clerical or procedural distinction, as the company says, or a way to reduce the conservation payment, as the complainant and the opposition suggest. A second question is whether the work stoppage reflects a violation, as the forest department’s notice reportedly states, or whether the company can show it had the permissions it needed for the activity under way. A third is whether the state’s accounts of what it accepted can be reconciled.
The project is still awaiting consideration by the National Board for Wildlife, and the Union Environment Ministry and the state are continuing their inquiries.
What to watch
Look out for the findings of the state and central inquiries, any reply from the company to the notice, and whether the National Board for Wildlife takes up the proposal. Whether the department recalculates the 4% deposit on the Rs 5,675 crore estimate will be the clearest sign of how it resolves the dispute.